Steel structure is the most common structure in our architectural structure design, so the project cost is relatively high. If we require the budget of steel structure project, how to do it?Next, the steel structure engineering cost company will give you a detailed explanation:
Composition of steel structure workshop
1、 Pricing basis of comprehensive unit price method for steel structure engineering
1.Bidding documents of the owner.
2. construction drawing design of steel structure engineering.
3.Relevant technical specifications, procedures and construction requirements, etc.
4. construction site conditions and requirements.
5, market price information of labor, materials, machinery, etc.
6. management and technical level of construction enterprises in the region.
7. other factors to be considered.
The bidding of steel structure construction enterprises should also consider their own management level and bidding strategy.
2、 Calculation sequence of comprehensive unit price method for steel structure engineering
1. study relevant documents, specifications and procedures.
2.Be familiar with quota and site conditions.
3.According to the sub items of the bill of quantities and the comprehensive contents of the bill, the direct cost of the sub items of the bill shall be determined according to the pricing basis.
4. indirect expenses and profits tax shall be calculated according to the determined rate.
5.Add up and combine the direct cost, indirect cost, profit and tax into the unit price of the whole cost.
In the process of bidding in some regions, when the quotation is lower than the total cost unit price of the guidance fee rate (excluding the payment of various social security funds stipulated by the state), the owner will make a careful analysis, which may be considered as lower than the cost quotation and not accepted.
Post time: Jun-15-2020